So I have about 14 servers that are on Version 15.5 (I know, but if it aint broke don't fix it)., and I have been tasked with upgrading them to v16. The existing servers are Windows 2008R2 (all VMWARE guests), and the new servers will be Server 2016. I have put together the following process for upgrading and migrating and just want to see if it sounds good to the people who have much more experience with this:
1. Get new server ready (fully patched)
2. Install latest version of 3cx
3. Backup old server database
4. Decommission old server -- copy templates from old server to new server -- remove from domain power down.
5. Rename new server to the old server name -- also change IP to old server IP.
6. Restore/Migrate from latest backup
7. Call 3cx to get the new server activated
8. reinstall 3rd party tools (voiptools) and work with 3rd party to get activated.

I understand that step 4 and 5 will incur downtime of the phone systems, but I work for k-12 education and School is out for summer, so having a small windows of downtime is not an issue. Is there anything I am missing in these steps? Is there a better way to go about doing this?

Thanks!!!
 
You steps are slightly wrong - https://www.3cx.com/docs/upgrading-pbx-v16/.

You can not install 3CX onto new server, until you have switched off the old server - at least stop it accessing the internet. You can not have two servers running at the same time with the same license key and fqdn as the 3CX software calls home.
 
Last edited:
Thank you!!! I will adjust my steps.
 